China-Laos mega power project put into operation

By Li Yingqing and Yan Yujie in Kunming | chinadaily.com.cn | Updated: 2026-04-21 14:28

An electrician works on the China-Laos 500-kilovolt power interconnection project in February. [Photo provided to chinadaily.com.cn]

Jointly invested by China Southern Power Grid and Electricite du Laos Transmission Company, the project connects Xishuangbanna Dai autonomous prefecture in Yunnan province with Oudomxay and Luang Namtha provinces in Laos. The transmission line spans 177.5 kilometers, including 145 km in China and 32.5 km in Laos.

A 500 kV substation has been newly built in Laos, along with two 230 kV transmission lines linking the country's northern backbone grid, to support the development of a unified national power network.

This year marks the 65th anniversary of the establishment of China-Laos diplomatic relations and the Year of China-Laos Friendship.

Global Edition
BACK TO THE TOP
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.