On 23 December, 2015, the Qatar Mega Reservoir Package E, constructed by CGGC, has achieved remarkable progress in contract performance. The water-supply pipeline installation, the first node of this project, was launched 15 days ahead of the planned date, setting a good beginning for project management and laying a solid foundation for its overall performance.
Jobsite of the bypass-pipe interconnection and installation |
The first node work of Qatar Mega Reservoir Package E includes the installation of the DN1200-1600mm pipe as long as 11.2km, containing 14 valve stations and 16 anchorage blocks along the line. The members of the Project Department have acquitted themselves well in examining suppliers, making orders, inspection, transportation, customs clearance, external corrosion prevention, pipe ditch excavation and other preparations. Currently, they are engaged in constructing the valve station and anchorage block. As the first supplier participating in node construction of this engineering contract, the joint venture led by CGGC has been highly praised by the project owner for its outstanding progress, excellent quality and effective on-site management.