CHINA> Gorgeous Project
|
China Yangtze Three Gorges Project (TGP) introduction
Updated: 2007-04-16 10:29
The total period of TGP construction is 17 years, which can be divided into three phases. Phase I (1993~1997) was designed mainly to do advance work for project construction and excavation of diversion channel with the river close-off as the milestone. Phase II (1998-2003) was mainly designed for construction of spillway and left-bank power house and the ship lock, with the completion of initial water storage, commercial operation of first batch of generators and ship lock open to navigation as several significant milestones of this phase. Phase III (2004-2009) has the main task of construction of right-bank dam and powerhouse, which is symbolized as the commercial operation of all the generator units and completion of the project.
|