Comprehensive plan issued for Beijing's new airport

chinadaily.com.cn | Updated: 2018-07-06 15:09

An aerial photo shows the construction site of Beijing's new airport in southern Daxing district in Beijing. The new international airport is taking shape and already has a roof in March. [Photo by Yang Zhiyong/chinadaily.com.cn]

The acceptance check for Beijing's new airport and auxiliary projects has been set for June 30, and three months later, the airport will be put into operation on Sept 30, 2019, according to a comprehensive plan issued Friday.

The comprehensive plan issued at a meeting covers the leftover construction work of the airport, the acceptance check work, transfer plan, preparatory work for formal operations, reception plan and other relevant special plans.

Feng Zhenglin, head of the Civil Aviation Administration of China, said at the meeting Friday that the plan has set some important time frames for the new airport project to be put into operation on schedule.

The new airport north line expressway will be available for traffic in December, the ground refueling facilities should be ready in April, and the new airport expressway will be ready for traffic in June.

When the new airport is in operation, the core work area, life service area, freight area and supporting facilities in the first phase should be in use for China Eastern Airlines and China Southern Airlines.

The Beijing-Xiongan intercity high-speed railway should be operational. Meanwhile, the new subway line linking downtown Beijing and the airport, the new airport expressway and north line expressway should all be in use.

Authorities have urged related units to push ahead with construction work and preparatory work for operations at the same time. Some 92 percent of the flight area and 42 percent of road projects have already been finished.

The terminal has been completed, and interior decoration and equipment installation are underway. The west air control tower will be finished in June, and construction of the east tower is pushing forward.

Related units are urged to push ahead with work on personnel training, management mode research, organizational structure research, aviation business research and the compilation of an airport handbook.

Global Edition
BACK TO THE TOP
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.