This unit is manufactured by DEC, China. Milestones for its installation by the TGP RB E & M Installation Division of CGGC are as follows.

July 17,2007, started to install;

May 5, 2008, rotor put into place;

June 19,2008, installation and dry commissioning completed;

June 20, 2008, water filling and start-up test succeeded;

June 30,2008, 72-hour commissioning succeeded

 