Home / Our Business / Equipment Installation

Equipment Installation

CGGC is capable of installing turbo-generator units, electrical and auxiliary equipment of four 1,000MW hydropower projects simultaneously and its business covers various types of turbines such as Francis, axial-flow, pumped storage, tubular, and Pelton.

In the Three Gorges Project, CGGC created a world record of installing and putting into operation four large units (700MW each) within one year; in recent years, CGGC has installed over 50% of China’s total hydropower capacity, and is the established leader in hydropower unit installation in China and even the world.

 

Electromechanical Equipment Installation at the FAN Hydropower Station (Ethiopia)

CGGC was the general contractor of FAN Hydropower Station in the form of EPC and undertook all the installation work of its electromechanical equipment and sub-systems.

Read more

 

Installation of Impulse Turbine Generator Units at the Houay Lamphan Gnai Hydropower Station (Laos)

As general contractor of the Houay Lamphan Gnai Hydropower Station in the form of EPC, CGGC undertook the supply, installation and debugging of two 44MW impulse turbine generator units and subsystems.

Read more

 

Installation of Bulb Tubular Turbine Generator Units at the Wangfuzhou Hydropower Station (China)

The Wangfuzhou Hydropower Station is equipped with four 27.25MW bulb tubular units to reach a total installed capacity of 109MW, generating 581 million KWH of electricity per year.

Read more

 

Installation of Impulse Turbine Generator Units at the Yele Hydropower Station (China)

CGGC installed two 120MW high-head impulse turbine generator units (with a maximum water head of 640m) for this project, China's then largest Pelton turbine generator units in terms of single-unit capacity.

Read more

 


   3 Next  

 

Links Privacy Statement Terms of Use Contact Us

Copyright@2013 China Gezhouba (Group) Corporation. All rights reserved.